Monday 15 February 2016

How to make EARTH WORKS properly when installing Fiberglass Pool

We have many questions about earth works before installing the pool. It's very important matter to do it properly because it influences later condition of Your fiberglass swimming pool. So in this short post I want to explain how to prepare the ground in a propper way  before installing fiberglass pool.
How to make an excavation for inground fiberglass pool

1. En excavation

First construct an excavation pit in order to house the swimming pool taking into consideration the depth of the foundation slab. The size of the excavation pit constitutes the diameter of the swimming pool framework increased by 60-80 cm from each side – in order to ensure the proper conveyance of installation and piping works.







The process of swimming pool foundation shall take place on the original ground not on back ll soil. The soil congestion coe cient shall amount to the swimming pool load, which amounts to 1600 kg/m2. In case of existence of ground or layer waters in non permissible soils (clay, loam) the bottom layer should be supported, by a well congested thick grain soil of the thickness 20cm as well as additional drainage belt.



How to prepare an excavation in the garden for swimming pool

Preparing foundation slab for fiberglass pool















2. Founadtion slab

The size of the slab is equal to the external upper edge of each swimming poolIt is recommended to manufacture a bottom layer below the level of ground and surface water deposits/streams. The hardened soil foundation has been engineered to house the reinforced concrete foundation slab of its total thickness amounting to h=12cm. The size of the slab is equal to the external upper edge of each swimming pool. Reinforced concrete class B20. The reinforcement is done with application of 8mm diameter ribbed steel bar mesh of the opening size every 20cm. Remember that layer have to be leveled perfectly .

The foundation slab is a smooth mortar surface, any surface slopes shall not amount to more than 0,5%

3. Styrofoam layer

The swimming pool is to be placed upon the foundation slabThe foundation slab is a smooth mortar surface, any surface slopes shall not amount to more than 0,5%. All works should be consulted with a construction specialist well acquainted to local ground conditions. The swimming pool is to be placed upon the foundation slab, should it still possesses slight unevenness, the slab should be levelled with a styrofoam layer.

Placing fiberglass pool in an excavation



3 comments:

  1. This is very fantastic blog and very useful and interesting information about the Manufacturer of Fiberglass Pools nice blog.
    Fiberglass Pools and Spas

    ReplyDelete
  2. IT very good and very nice and useful information about the Manufacturer of Fiberglass Pools i really like it.
    Manufacturer of Fiberglass Pools & Spas

    ReplyDelete
  3. Thank You Isabel very much for Your comment. We know that buying and installing Your dreamed swimming pool can be easier and faster if You have good advices. In DreamPools we want to help. Best regards

    ReplyDelete